Rapid progress

Although the range of works connected with the thermal efficiency improvement is wide, some progress can already be seen. Nearly all the windows (95%) in the building are replaced. The  insulation and elevation are being done. You can already admire first results – the elevation of the West wall of the building is finished. The thermal centre is also being modernised.